PrepAway - Latest Free Exam Questions & Answers

Which Process have you left out??

You are the project manager of a project. You have just complete the Define Activities, activity resources estimating and Estimate Activity Durations processes. Which Process have you left out??

PrepAway - Latest Free Exam Questions & Answers

A.
Control Schedule

B.
Create WBS

C.
Sequence activities

D.
Operations

Explanation:
The PMBOK places Sequence activities between Define Activities and Estimate Activity Resources.