When can pre-assigmnet of the project team members occur?
A.
Whe the project uses capital expenditures
B.
When the required staff can be acquired from outsides sources
C.
When the project would be ignored due to travel expenses
D.
When the project is the result of specific people being promised as part of a competitive proposal