PrepAway - Latest Free Exam Questions & Answers

Which of the following is a project constraint?

Which of the following is a project constraint?

PrepAway - Latest Free Exam Questions & Answers

A.
Twenty-five percent sataff turnover is expected

B.
The technology to be used is cutting-edge

C.
Project leadership may change due to volatile political environment

D.
The product is needed in 250 days.


Leave a Reply