PrepAway - Latest Free Exam Questions & Answers

Which one of the following is true regarding the change control board?

Which one of the following is true regarding the change control board?

PrepAway - Latest Free Exam Questions & Answers

A.
Describes how changes are managed?

B.
Approves or rejects change requests

C.
Needs updated project management plans to approve or reject a change.

D.
Describes how changes are documented

Explanation:
Change control board can be referred to as a board or committee or group of stakeholders, that analyze and review the change requests that have been forwarded by the project management team and accordingly take decision whether the change request needs to be accepted or rejected.

*Consists of stakeholders.
*Approve or reject changes.
*Decisions are often accepted and considered final.
*Role clearly defined.
*All change requests should go through it.