In three point estimating technique, if the most likely estimates for an activity to completes is 100 days, the optimistic estimates is 60 days and the pessimistic estimates is 200 days, what is the expected duration in which the activity will be completed?

PrepAway - Latest Free Exam Questions & Answers

A.
90 days

B.
100 days

C.
110 days

D.
660 days

Explanation:
Ed= (Mop + 4Mest + Mpes)/6