The project integration Management Knowledge area includes which of the following set of processes?
A.
Develop project charter, direct and manage project Execution Perform integrated Change Control
B.
Define Project Scope, Create WBS, Close Project or Phase
C.
Develop project charter, Develop Human Resource Plan, Estimate Cost
D.
Identify Stakeholders, plan communications, develop Project Management Plan.