You are the project manager of a project. You have just completed the collect Requirement and Define Scope. What should you do next?
A.
Create WBS
B.
Verify Scope
C.
Value analysis
D.
Control Scope
Explanation:
Create WBS is the process that follows collect Requirement and Define Scope