PrepAway - Latest Free Exam Questions & Answers

which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

PrepAway - Latest Free Exam Questions & Answers

A.
WBS directory

B.
Activity list

C.
WBS

D.
Project schedule

Explanation:
Work breakdown structure, WBS, is a project management technique initially developed by the US Defense Establishment, which deconstructs a project with the intent to identify the deliverables required to complete the project. The project management work breakdown structure, WBS, is utilized at the beginning of the project to define the scope, estimate costs and organize Gantt schedules.
Work breakdown structure, WBS, captures all the elements of a project in an organized fashion. Breaking down large, complex projects into smaller project pieces provides a better framework for organizing and managing the project. WBS can facilitate resource allocation, task assignment, responsibilities, measurement and control of the project.


Leave a Reply