Which document contains initial requirements that satisfy stakeholders needs and expectations?
A.
Project charter
B.
Project management plan
C.
Project statement of work
D.
Project scope statement
Explanation:
A Project Charter is a formal document that authorizes the start of a project. It names and appoints a project manager, assigns a summary budget, establishes a project time line, and documents key assumptions and constraints. The project boundary, its key deliverables – the mission of the project are documented as much as possible.A Project management plan is the planning document, capturing the entire project end-to-end, covering all project phases, from initiation through planning, execution and closure.