Which document contains initial requirements that satisfy stakeholders needs and expectations?

Which document contains initial requirements that satisfy stakeholders needs and expectations?

PrepAway - Latest Free Exam Questions & Answers

A.
Project charter

B.
Project management plan

C.
Project statement of work

D.
Project scope statement

Explanation:
A Project Charter is a formal document that authorizes the start of a project. It names and appoints a project manager, assigns a summary budget, establishes a project time line, and documents key assumptions and constraints. The project boundary, its key deliverables – the mission of the project are documented as much as possible.

A Project management plan is the planning document, capturing the entire project end-to-end, covering all project phases, from initiation through planning, execution and closure.