Which of the following activities is not part of Plan Risk Management?

Which of the following activities is not part of Plan Risk Management?

PrepAway - Latest Free Exam Questions & Answers

A.
Updating Risk register

B.
Determining risk roles and responsabilities

C.
Identifying risk categories

D.
Developing a risk management plan

Explanation:
Updating Risk register first happens in Identify Risk Phase. Determining risk roles and responsabilities, Identifying risk categories, and Developing a risk management plan are part of Plan Risk Management