which of the following scope management processes is the scope management plan prepared?

A scope management plan, in which of the following scope management processes is the scope management plan prepared?

PrepAway - Latest Free Exam Questions & Answers

A.
Initiation

B.
Collect Requirements

C.
Define Scope

D.
Verify Scope

Explanation:
Scope management plan is one of the major Scope communication documents. The Project Scope Management Plan documents how the project scope will be defined, managed, controlled, verified and communicated to the project team and stakeholders/customers. It also includes all work required to complete the project. The documents are used to control what is in and out of the scope of the project by the use of a Change Management system. Items deemed out of scope go directly through the change control process and are not automatically added to the project work items. The Project Scope Management plan is included in as one of the sections in the overall Project Management plan. It can be very detailed and formal or loosely framed and informal depending on the communication needs of the project.


Leave a Reply