Which of the following is not part of the project cost baseline but is included in the project budget?

Which of the following is not part of the project cost baseline but is included in the project budget?

PrepAway - Latest Free Exam Questions & Answers

A.
Management Contingency Reserve

B.
Management Overheads

C.
Project management Planing

D.
Activity Cost Contingency Reserve

Explanation:
The diference between the Cost Baseline and Funding requirement at Project competion is Mnagement Contingency Reserve Management Contingency Reserve is NOT part of aproject Baseline.