Reviewing, tracking, and regulating the process to meet performance objectives defined in the project management plan are part of which process?

PrepAway - Latest Free Exam Questions & Answers

A.
Monitor and Control Project Work

B.
Direct and Manage Project Execution

C.
Monitor and Control Risk

D.
Perform Integrated Change Control