Which of the following documents allows the project manager to assess risks that may required near term action

Which of the following documents allows the project manager to assess risks that may required near term action?

PrepAway - Latest Free Exam Questions & Answers

A.
Probability and impact matrix

B.
Contingency analysis report

C.
Risk urgency assessment

D.
Rolling wave plan