Which of the following is NOT an input of Estimate Costs?
A.
Earn Value Analysis
B.
Scope Baseline
C.
Risk Register
D.
Human resources plan
Explanation:
Earn Value Analysis is used during the execution of the project to determine resource consumption versus planned