_________________ Is always the lowest risk for the buyer if the scope of work is not well defined

_________________ Is always the lowest risk for the buyer if the scope of work is not well defined

PrepAway - Latest Free Exam Questions & Answers

A.
Purchase order

B.
Fixed Price

C.
Time and material

D.
Cost plus incentive fee

Explanation:
What is Cost Plus Incentive Fee (CPIF)?
Pays all cost an agreed upon fee plus a bonus for beating the performance objective stated in the contract.