Wich Schedule development technique modifies the project schedule to account for limited resources?

A.
Human resource planning
B.
Fast Tracking
C.
Critical Chain method
D.
Rolling Wave planning
Explanation:
Critical Chain Project Management (CCPM):
According to PMBOK Critical chain method is a schedule network analysis technique that modifies the project schedule to account for limited resources. It mixes deterministic and probabilistic approaches to schedule network analysis. The critical chain concept was coined by Eliyahu Goldratt. Following few sections briefly describe the concepts Critical Chain depends on and are useful to understand the example that will follow shortly after that.