PrepAway - Latest Free Exam Questions & Answers

Which process involves identifying and documentating the logical relationships among activities?

Which process involves identifying and documentating the logical relationships among activities?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule development

B.
Activity sequencing

C.
Create WBS

D.
Applying leads and lags

Explanation:
The Activity Sequencing process involves the identification and documentation of the logical relationships among schedule activities. Schedule activities can be logically sequenced with appropriate precedence relationships, leads and lags to enable a realistic, achievable project schedule. Sequencing may be performed using project management software and/or manual techniques.


Leave a Reply