Which of the following risk management processes uses brainstorming as a technique?

A.
Identify Risk
B.
Monitor and control Risk
C.
Plan Risk Management
D.
Plan Risk Responses
Explanation:
Brainstorming the Project
Brainstorming is likely the most common approach to risk identification. Its usually completed together as a project team to identify the risks within the project. The risks are identified in broad terms and posted, and then the risks characteristics are detailed. The identified risks are categorized and will pass through qualitative and quantitative risk analysis later.