The decision to approve or reject a particular change request is made in which of the following processes?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform integrated Change Control

B.
Monitor and control Project work

C.
Develop Project Management Plan

D.
Direct and Management Project Execution