Which of the following is one of the tools and techniques for the Define Activities Process?

A.
Rolling wave planning
B.
Dependency determination
C.
Schedule network template
D.
Applying leads and lags
Explanation:
Rolling wave planning is the process of planning for a project in waves as the project becomes clearer and unfolds. It is important in such projects to at least highlight in the initial plan the key milestones for the project.