Which of the following is a tool or technique used to verify scope?

A.
Product analisys
B.
Ishikawa diagram
C.
Inspection
D.
Requirements Traceability Matrix
Explanation:
The term inspection refers to one of the most critical elements of the entire process that surrounds the execution and successful completion of a given project. The term inspection refers specifically to the act in which the project management team, project management team leader, or other interested and significant parties take the effort to go review the entirety of the project in meticulous detail to determine whether or not the project meets certain predetermined requirements for completion.