Which of the following activities is not part of Plan Risk Management?

A.
Updating Risk register
B.
Determining risk roles and responsabilities
C.
Identifying risk categories
D.
Developing a risk management plan
Explanation:
Updating Risk register first happens in Identify Risk Phase. Determining risk roles and responsabilities, Identifying risk categories, and Developing a risk management plan are part of Plan Risk Management