You are the project manager for a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (Wooden Coated). This is an example of which of the following?

A.
Risk
B.
Assumption
C.
Constraints
D.
Budget
Explanation:
A and C are incorrect because the scenario did NOT describes a risk or constraint.This is an example of assumptions because estimates provided will be accurate if the rooms meet the requirements like (Wooden Coated)