PrepAway - Latest Free Exam Questions & Answers

which of the following?

You are the project manager for a project. Project is a global project. Some peoples are working from US and some are from India. Client says budgets should no cost more than $12 millions. Because of the global concerns, the final budget must be in U.S. dollars. This is an example of which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Internationalization

B.
Budget constraints

C.
Management constraints

D.
Quality constraints

Explanation:
This is an example of Budget constraints. The budgets must not exceed $12 millions.

Budget constraint are anothe element of the classic Triple constraint (Cost, schedule, Scope). Budget limit the project teams ability to obtain resources and might potentially limit the scope of the project. For example Component X cannot be part of this project, because the budget does not support it.


Leave a Reply