PrepAway - Latest Free Exam Questions & Answers

what you tell?

If aproject with a CPI of 1.2 what you tell?

PrepAway - Latest Free Exam Questions & Answers

A.
The project is consumed fewer resources than anticipated

B.
The project is using fewer resources than anticipated

C.
The project is falling behind

D.
The project is running ahead of schedule