You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You inmmediately set-up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?

A.
Functional
B.
Balanced Matrix
C.
Projectized
D.
Strong Matrix