What is the status of the project if the cost Performance index is 1.25 and the schedule Performance Index is 0.75?

A.
Under budget and behind schedule
B.
Over budget and ahead of schedule
C.
Under budget and ahead of schedule
D.
Over budget and behind schedule
Explanation:
CPI = EV / AC