Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

A.
4
B.
6.3
C.
6
D.
6.1
Explanation:
Simple Average Duration Estimate = (O + M + P)/3PERT Duration Estimate = (O + 4M + P)/6