The project manager calculated a schedule performance index 0.80 and a cost performance index 1.1 for the project. What is the actual status of this project?

A.
Behind the schedule and over budget
B.
Behind the schedule and under budget
C.
Ahead of schedule and under budget
D.
Ahead of schedule and over budget
Explanation:
Schedule performance Index (SPI) = EV/PV is an indicator whether the project is on time (SPI = 1) or behind the schedule(<1).Cost performance Index (CPI) = EV/AC is an indicator whether the project is incurring expenses more than (CPA<1)/less than(CPI >1)/ equal to (CPI = 1)