What is an output of Control Scope?

A.
Accepted deliverables
B.
Work performance measurements
C.
Requirements documentation
D.
Work performance information
Explanation:
Control Scope process involves monitoring the status of project and managing scope changes.
The answer should be (D) Work performance information base on PMBOK edition 5th, page 139.