During the planning phase of your project, your project team members have discovered aanother way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of ____________

PrepAway - Latest Free Exam Questions & Answers

A.
Alternative selection

B.
Assestment

C.
Alternative identification

D.
Product analysis