During the planning phase of your project, your project team members have discovered aanother way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of ____________

A.
Alternative selection
B.
Assestment
C.
Alternative identification
D.
Product analysis