Project scope is________________

A.
The features and functions that are to be included in a product or service
B.
The work that must NOT be done in order to deliver a product with the specified feature and function
C.
Part of the project charter
D.
Part of sow
Explanation:
The work that must be done in order to deliver a product with the specified feature and function or The features and functions that are to be included in aproduct or service