At the completion of week 16 of the project, the following information is collected Actual cost $50,000 Plan

The project budget is set at $150,000. The project Duration is planned be one year. At the completion of week 16 of the project, the following information is collected
Actual cost $50,000
Plan cost $45,000
Earned Value $40,000
What is the cost performance index

PrepAway - Latest Free Exam Questions & Answers

A.
0.80

B.
0.89

C.
1.13

D.
1.25