Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Risk response planning
B.
Risk monitoring and controlling
C.
Performance reporting
D.
Manage stakeholders
Explanation:
Performance Reporting is:
The process of gathering and communicating information regarding the current status of a project as well as projections for progress over time.
Durng performance reporting:Information regarding the work being accomplished
resources being used is collected, analysed and displayed in various report formats.