The project budget is set at $150,000. The project Duration is planned be one year. At the completion of week 16 of the project, the following information is collected
Actual cost $50,000
Plan cost $45,000
Earned Value $40,000
What is the cost performance index

A.
0.80
B.
0.89
C.
1.13
D.
1.25