PrepAway - Latest Free Exam Questions & Answers

You should calculate the forecast using which of the following methods?

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?

PrepAway - Latest Free Exam Questions & Answers

A.
BAC

B.
EAC

C.
ETC

D.
WBS


Leave a Reply