What is MOST likely to be affected?

A problem occurs on an activity with free float and the project manager has extended its duration.
What is MOST likely to be affected?

PrepAway - Latest Free Exam Questions & Answers

A.
Project duration

B.
Resource schedules

C.
Project scope management plan

D.
The latest start for the successor activity