You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process group. You’ve published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and who will prepare it is which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Scope management plan

B.
Project charter

C.
Communications management plan

D.
Information distribution plan

Explanation:
The communications management plan documents what information will be distributed, how it will be distributed, to whom, by whom, and the timing of the distribution.