Executing the risk response plan in order to react to risk events throughout the project is called:

Executing the risk response plan in order to react to risk events throughout the project is called:

PrepAway - Latest Free Exam Questions & Answers

A.
Contingency planning.

B.
Monitoring and control.

C.
Mitigation.

D.
Life cycle costing.