Which of the following can result from fast tracking?

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

PrepAway - Latest Free Exam Questions & Answers

A.
The risk of achieving the shortened project time is increased.

B.
The critical path will have positive total float.

C.
Contingency reserves are released for redeployment by the project manager.

D.
Duration buffers are added to maintain a focus on planned activity durations.

One Comment on “Which of the following can result from fast tracking?

  1. Ahmet Can Aykut says:

    I think C would be a better answer because of rework that would be caused by fast tracking.

    Plz refer to PMBOK v5

    “Overlapping phases may require additional resources to allow work to be
    done in parallel, may increase risk, and can result in rework if a subsequent phase progresses before
    accurate information is available from the previous phase.”