Which of the following could happen if you don’t correct this?

You are a project manager for Giraffe Enterprises. You’ve recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition. Which of the following could happen if you don’t correct this?

PrepAway - Latest Free Exam Questions & Answers

A.
The project costs could increase, there might be rework, and schedule delays might result.

B.
The project management plan’s process for verification and acceptance of the deliverables needs to be updated as a result of the poor scope definition.

C.
The poor scope definition will adversely affect the creation of the work breakdown structure, and costs will increase.

D.
The stakeholders will require overtime from the project team to keep the project on schedule.

Explanation:
Option A might seem like a correct answer, but option D is more correct. There isn’t enough information to determine whether stakeholders will require overtime. We do know that poor scope definition might lead to cost increases, rework, schedule delays, and poor morale.