The Project Integration Management knowledge area includes which of the following set of processes?

The Project Integration Management knowledge area includes which of the following set of processes?

PrepAway - Latest Free Exam Questions & Answers

A.
Develop Project Charter, Direct and Manage Project Execution, Perform Integrated Change Control

B.
Define Project Scope, Create WBS, Close Project or Phase

C.
Develop Project Charter, Develop Human Resource Plan, Estimate Costs

D.
Identify Stakeholders, Plan Communications, Develop Project Management Plan