A project manager is assigned to a project which phase of the project?

A project manager is assigned to a project which phase of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Closing

B.
Initiation

C.
Estimation

D.
Planning

Explanation:
In the Initiation phase, the sponsor releases resources to get the project done, and the project manager is chosen.