PrepAway - Latest Free Exam Questions & Answers

The scope of a project can be expected to change if:

The scope of a project can be expected to change if:

PrepAway - Latest Free Exam Questions & Answers

A.
The project manager must provide cost estimates without having a design concept

B.
All of the other alternatives apply are possible based upon the situation

C.
The project manager is assigned after the project is defined, and the cost and schedule are approved

D.
A clear objective is not provided

E.
Oversimplification (underestimating) of the nature of the work occurs


Leave a Reply