What is the CPI of this project?

You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower’s site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300, AC = 200, and EV = 250. What is the CPI of this project?

PrepAway - Latest Free Exam Questions & Answers

A.
0.83

B.
0.80

C.
1.25

D.
1.5

Explanation:
CPI is calculated as follows: EV AC. In this case, 250 200 = 1.25.