In which type of organization(s) is the project manager’s role most likely part-time?

In which type of organization(s) is the project manager’s role most likely part-time?

PrepAway - Latest Free Exam Questions & Answers

A.
Functional

B.
Weak Matrix

C.
Balanced Matrix

D.
Both 1) Functional and 2) Weak Matrix