PrepAway - Latest Free Exam Questions & Answers

What is the cost variance?

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.

What is the cost variance?

PrepAway - Latest Free Exam Questions & Answers

A.
-$700

B.
-$200

C.
+$200

D.
+$500


Leave a Reply