Which process group can be performed outside the project’s scope of control?
A. Planning
B. Monitoring and Control
C. Closing
D. Initiating
2 Comments on “Which process group can be performed outside the project’s scope of control?”
Ahmet Can Aykutsays:
Totally wrong question and wrong answer.
0
0
Ahmet Can Aykutsays:
“Initiating processes may be performed at the organizational, program, or portfolio level and therefore, would
be outside of the project’s level of control.”(Refer to 3.3 PMBOK v5)
Totally wrong question and wrong answer.
0
0
“Initiating processes may be performed at the organizational, program, or portfolio level and therefore, would
be outside of the project’s level of control.”(Refer to 3.3 PMBOK v5)