Which describes how cost variances will be managed?

Which describes how cost variances will be managed?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost management plan

B.
Cost baseline

C.
Cost estimate

D.
Chart of accounts

Explanation:
Cost management plan describes how cost variances will be managed.